Package Migration - Detailed Dimension Change - Check/Uncheck Confirm for Long Changes
Mark the issue as Confidential to keep log files and screenshots private
1. Product versions:
- OS and Version: Microsoft Windows Server 2019 Datacenter Server 10.0.17763 Build 17763 (x86_64)
- TM1/PA Version: 11.8.00800.5
- Pulse Version: 6.0.5
- Browser: Chrome
3. Describe the bug
When I'm migrating a package, in the Review Changes page, I select a dimension. In the bottom table Detailed Changes, there is this column Confirm, where I can check / uncheck each dimension's change.
For some other dimensions in my package, I can’t confirm each change because it’s just an icon , i.e., the option seems to be disabled, as you can see in the screenshot.
4. To Reproduce
Steps to reproduce the behavior:
- Go to Migration > View Package > Select a package
- Click on Execute > Select a server > Select an instance > Select options
- Click Next
- Select a Dimension in the Proposed Changes table and click on Review Changes
- Detailed Changes expand on the bottom and shows static check marks in the Confirm column, instead of showing a Check/Uncheck control object
5. Expected behavior
I'd like to be able to check/uncheck each individual dimension's change even though the number of changes in the dimension is high.
6. Screenshots