View name is not shown in a process which has a View data source
** Key Information (please complete the following information):**
- Operating System: Windows Server 2008 R2
- TM1 Version: 2.0.6
- Browser: N/A
- Arc clients: Web
- Arc Version: 4.0.0
- Excel Version: 365 64 bit
Describe the bug
When opening a process which has a data source of a TM1 Cube View, the cube name is shown, but the view name is not. It is in Perspectives:
Maaaaaybe this is by design but I can't think of a good reason for it to be different in Arc.
Granted, a lot of the time a lot of admins will be generate the view dynamically on the Prolog tab rather than using a fixed, public view. However there are exceptions, notably with ad hoc or historical view based processes, and if you need to modify the data source manually... it's useful to know which one it is.
To Reproduce
Steps to reproduce the behavior:
- Create a public view of a cube;
- Create a new process;
- Assign the public view as the datasource for the process;
- Close and reopen the process;
- There will be no information about the view name that serves as the data source.
Expected behavior
The data source name of the view should be shown in the drop-down.
Logs and Errors
N/A
Screenshots
Attached above.
Additional context
At the moment I usually go back to Perspectives to check the view name in cases like this.